Subject: Railway Road Changes

Reference: LBR-FOI-00822

I would like to know the costs associated with making the planned changes to the road and footpath of Railway Road, Teddington, TW11. These changes include, but are not limited to, imposing car parking on the kerb and footpath; painting double yellow lines the length of the road; and other road marking changes.

Response

Full Disclosure - 1 March 2023

I would like to know the costs associated with making the planned changes to the road and footpath of Railway Road, Teddington, TW11. These changes include, but are not limited to, imposing car parking on the kerb and footpath; painting double yellow lines the length of the road; and other road marking changes.

Communication/consultation printing & delivery: £500

Implementation : £2,200

Staff time: £5,000

Contingency: £1,500

Total: £9,200

NB1. Costs are estimates at this stage and apply to completion.

NB2. Costs do not include any strengthening work that may need to be carried out to the footway.